Client Adco Construction
Location Melbourne
Scope Of Work Mechanical Services/HVAC
Schedule 2015-2016

Project Detail

HVAC Project Summary

This prestigious community centre with HVAC works valued at $2m was awarded to Insulpak as the “Preferred” Contractor.  This project required the supply and installation of chillers, boilers, AHU’s which services multiple function rooms, kitchens, cafes and offices.

Skills and Equipment Used

Insulpak’s Project management team, supervisors and experienced tradesman all worked closely together to co-ordinate crane lifts, deliveries and software application tools to communicate effectively to ensure efficient installation of equipment and ensure the project was running smoothly and according to schedule.

Challenges of the HVAC Installation

This project consisted of 34 continuous crane lifts to place all the equipment on the roof of the building, therefor communication and co-ordination was the key.

The enormous amount of equipment and components being delivered on site at one time required the logistics to be well planned as there were often 3-4 deliveries per day.

HVAC Project Outcome

Through the continuous efforts of our Project Management, Supervisors and Plumbing team, Insulpak have delivered this HVAC project on time and of a high standard that we are most proud of.